Haridwar-Dehradun NH project to miss another deadline

Tuesday, 14 Nov 2017
Share this on :

The state government is unlikely to meet the November 2017 deadline for completion of the widening of Dehradun-Haridwar-Roorkee-Narsain National Highway.

The road widening work on the Haridwar-Dehradun project commenced on 1 November 2011 and was scheduled for completion on 30 October 2013. The project is being implemented under public-private partnership (PPP) mode.

Similarly, four laning work on the Haridwar-Muzaffarnagar NH commenced on 3 September 2010, and was scheduled to get over by 28 February 2013.

Only 65 percent of work has been completed so far in both the projects. Just three weeks are left for completion of the new deadline but still more than 35 percent work of the project is incomplete.


Related Projects:
Road Upgradation (Muzaffarnagar-Haridwar) Project
Road Upgradation (Haridwar-Dehradun) Project

Dehradun Highways Project Ltd.
Related Projects
1
Related Tenders
0
Roadways
Related Projects
28496
Related Tenders
207545
 
Post Your Comments
 
 
   
 

 

 
  
Projects Explorer App

Data Explorer - Facade Search - ProjectsToday

Free Trial Access

REGISTER AND GET STARTER KIT ABSOLUTELY FREE!

Free access to Project News and Analysis

Project and Tender Alert in your mailbox

Explore the largest Database on Projects for free

Be part of Online Projects Community

Username:

Start Exploring

Subscribe to any of our premium plans to

Access to complete information on 43000+ projects

Use our Notification service for instant update on projects and tenders

Closely monitor your opportunities with "WORKSPACE"

Use our online platform for promotions of your products and services