Flyover to be ready before April

25 February 2010: Work on the Bakery Junction flyover in Thiruvananthapuram is likely to be completed before 30 April 2010.

All work, including tarring, on the Kowdiar-Kuravankonam stretch will be completed before 25 March 2010. Work on the Kowdiar-Narmada road will be completed by 20 March, while that on the Ambalamukku-Peroorkada road will be completed before 15 May.

On the other hand, work on the Peroorkada-Vazhayila road, the KIMS bridge, the Chakka bridge and the Vellayambalam-Sasthamangalam stretch would be completed by 30 May, 30 April, 31 May and March end, respectively.

Source: Hindu