Shree Tatyasaheb k Sahakari Sakhar Karkhana is likely to sign the power purchase
agreement with Maharashtra State Electricity Board for the 2.5- mw mini, hydel
power project at Patqaon in Bhudargad taluka of Koihapur district is likely to
be signed by September this year.
The
project is estimated to cost Rs 15 crore and will be funded through bank loans
and remaining 10 per cent through internal accruals. Financial closure of the
project has been achieved.
At
present, civil work is under way and 60 to 70 per cent of project work is
complete with full completion of the project expected by the end of 2008.
Published
in Projectmonitor issue: April 21, 2008