Bharat Heavy Electricals (BHEL) has secured a contract from NMDC worth Rs 359 crore.
This is an order for a plant power distribution system package for its three million tpa integrated steel plant at Nagarnar, in Chhattisgarh. The company has already undertaken the process of executing a raw material package for this plant.
The scope of work involves designing, engineering, supply, erection and commissioning of the complete power distribution system on turnkey basis. This way, the system will provide power through 33 kV GIS based substations, to the shops of the steel plant.
With this order, BHEL has bagged its second package control from NMDC for the same plant.
More Project Info:
Integrated Steel (Nagarnar) Project