Bangalore International Airport (BIAL), is expected to commence operations for Terminal-1 (T1) in phases, commencing from October 2013.
The terminal-1 building is part of a Rs 1,200 crore expansion project of Bangalore international airport, on an aggregate area of about 1,34,000 sq mtr land. It will be designed to serve approximately 17.2 million passengers per annum. The new Airport Operational Control Centre (AOCC), is located at the east section of the terminal on the pier. Work on AOCC installation has been completed and trials of the check-in counters have begun. The AOCC is equipped with advanced processes to enable faster and quicker decision in real time and comes with a video wall to enable operators to have real-time information projection at a common visible area.