NHPC has invited RfQs for providing civil works for its 800 (4 x 200) MW, Tawang Stage-II, hydel-based power unit, in Arunachal Pradesh.
RfQs have been invited for the following civil works in three packages:
|
-
Lot-1: construction of diversion tunnel, barrage, intake, desilting chambers, silt flushing tunnels, part head race tunnel upto RD 1,944 mtr, to be completed in a time span of 65 months (Tender)
|
|
-
Lot-2: construction of head race tunnel from RD 1,944 mtr to RD 15,947 mtr, including Adit-II, III, IV and V, to be completed in 59 months (Tender)
|
|
-
Lot-3: civil works for construction of surge shaft, pressure shaft, underground powerhouse, tail race system and pothead yard, and part of head race tunnel from RD 15,947 mtr to RD 15,989 mtr, including Adit-VI, to be completed in a time span of 65 months (Tender)
|