NTPC has invited bids for the Tanda Thermal Power Project, Stage-II, coming up at Vidyut Nagar, in Uttar Pradesh.
Bids have been invited for the coal handling plant package for the 1,320 MW (2x660 MW) thermal power project.
NTPC is setting up the project with an investment of Rs 9,188.98 crore. The NTPC board of directors has approved the capex for executing the project.
L&T-MHPS Boilers was recently awarded a contract for design, engineering, supply, construction, erection, testing, commissioning and conducting performance guarantee of two coal-fired steam generator units at the Tanda power project.
More Tender Info:
Coal Handling Plant Package for Tanda Thermal Power Project
More Project Info:
Tanda Coal Based Power Project - Stage II