Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Kundli-Manesar-Palwal Expressway achieves financial closure

Monday, 08 Jan 2007
Share this on :

On 8 January 2007, KMP Expresssways, an SPV floated by DS Constructions, UK-based Apollo Enterprises and Hyderabad-based Madhucon Projects achieved financial closure for the construction of 135-km Kundli-Manesar-Palwal expressway project awarded by Haryana State Industrial and Infrastructural Development Corporation (HSIIDC).

The KMP Expressway, also known as the western peripheral expressway is the largest expressway project in the country on BOT basis. Out of the total cost of Rs.1,915 crore, the SPV has tied up a debt of Rs.1,149 crore, through a consortium of 12 banks/financial institutions led by IDBI. The arrangers for the debt are SBI Capital Markets and IDBI.

The expressway project envisages construction of the 135.6 km, access controlled expressway from NH-1 near Kundli (Sonipat) crossing NH-10 at west of Bahadurgarh, crossing NH-8 at Manesar (Gurgaon) and joining NH-2 near Palwal (Faridabad). Work on the project is underway and is scheduled for completion by July 2009.