Delhi Metro Rail Corporation (DMRC) has invited bids for contract CC 71 for work related to Mundka, Ajronda and Sarita Vihar of Phase-III of Delhi mass rapid transit system project.
Bids have been invited for the construction of multi-storied staff quarters at Mundka, Ajronda and Sarita Vihar.
The work, estimated to cost Rs 87 crore, is expected to be completed within 24 months.
DMRC is developing Phase-III of the Delhi mass rapid transit system project at a cost of Rs 35,000 crore. The project comprises six corridors in a total length of 69.57 km to metro network with 31.11 km of elevated section and 38.46 km of underground section with extensions to existing lines.
Related Link:
Tender
Project profile