On 11 September 2007, the Supreme
Court allowed the consortium of Reliance Energy (REL) and Hyundai Engineering
Construction Co (HDEC) to submit its bid for the Rs.2,600 crore Mumbai Trans
Harbour Link Project between Mumbai and Navi Mumbai.
The proposed order was passed, while
setting aside a judgment of the Bombay High Court upholding the exclusion of the
consortium from the second stage of bidding on the ground that it had not
fulfilled the criteria relating to net worth of Rs.200 crore. The period for
presenting financial bids is now extended by REL-HDEC up to 15 December 2007.
The Maharashtra State Road Development
Corporation had disqualified them from presenting their bid. The Bombay High
Court dismissed a writ petition filed by REL-HDEC and the present appeal is
directed against this judgment dated 4 June 2007.