Bharat Heavy Electricals (BHEL) has accepted a letter of intent (LoI) from MB Power (Madhya Pradesh) for the supply of critical equipment for the upcoming 1x800 MW Anuppur Thermal Power Project.
The LoI, accepted on 03.09.2025, covers the supply of a boiler, turbine, and generator (BTG) package for the supercritical technology-based power project in Madhya Pradesh. The estimated value of the order is approx. Rs. 2,600 crore, excluding GST. The boiler will be manufactured at BHEL’s Trichy plant, while the turbine generator will be produced at its Haridwar unit.
The company confirmed that a formal contract agreement will be executed shortly, and the supply completion schedule is of 58 months. This development reinforces BHEL’s leadership in the thermal power equipment space and its continued role in advancing India’s power sector through high-efficiency supercritical technology. The Anuppur project will further augment reliable power supply in the region.