Damodar Valley Corporation's (DVC) 1,200 MW (2x600 MW) coal based power
project at Raghunathpur in the Purulia district of West Bengal is underway with
commissioning scheduled for June 2011.
For Unit I, drum lifting is done, erection of boiler started on 25 March 2010
and hydro testing of boiler is scheduled for June 2010. Unit I is expected to be
on steam by March 2011.
Drum lifting for Unit II was completed on 4 April 2010 while hydro testing of
boiler is scheduled for September 2010. This unit is likely to commence power
generation by June 2011.
Reliance Infrastructure is the contractor for the project.