Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Unit-III of coal-based Thiruvallur plant commissioned

Saturday, 01 Mar 2014
Share this on :

On 28 February 2014, NTPC Tamil Nadu Energy Company commissioned Unit-III of its coal-based power unit in Thiruvallur district of Tamil Nadu.


NTPC Tamil Nadu Energy Company is a joint venture of NTPC and Tamil Nadu Electricity Board. Unit-III of the project entailed a capacity of 500 MW. With the commissioning of Unit-III, the entire project, comprising another two units, has been completed.


Unit-I of the power plant, with 500 MW capacity, was commissioned in November 2012, while Unit-II of the project, with 500 MW capcity, was synchronised in February 2013. The company has invested Rs 5,400 crore in the entire project.


With this, the total installed capacity of the NTPC group has reached 42,964 MW.

 