Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

BWSSB approves Cauvery Stage-V project pipeline work

Saturday, 17 Dec 2016
Share this on :
The Bangalore Water Supply and Sewage Board (BWSSB) has approved the Cauvery Water Supply Stage-V Project, on 15 December, 2016.

Approval was given to lay the 9.6 km water pipeline from Netkal Balancing Reservoir to Torekadanahalli (T K Halli) reservoir, which will supply 810 million ltr of water per day to the city.

The estimated cost of the project is Rs 160.33crore, of which Rs 80 crore will be borne by Karnataka Urban Infrastructure Development Finance Corporation, 40 crore by the state government, and Rs 40.33 crore by BWSSB.

The pipeline will draw raw water from Netkal Balancing Reservoir to T K Halli, where it will be treated and supplied to the city.

Following the completion of Stage-V, a total of 110 villages, covering an area of 225 sq km will be provided water.  

The treatment plants at Tataguni, T K Halli and Harohalli of Cauvery first and second stages will be replaced under the project, as they are around 50 years old.