Essar Energy on 28 October 2010 commissioned Unit I 220 MW of its Vadinar
power plant in Gujarat. The unit has been set up at a cost of $160 million
(approx Rs 712 crore).
The Phase I consists of 380 MW, comprising 220 MW (two units) of gas fuelled
power generation capacity and 630 tph of steam capacity. The entire power and
steam output will be sold under a long term contract to Essar Energy's Vadinar
oil refinery.
The Phase II of the project consists of a multi-fuelled (coal, naphtha, light
cycle oil, clarified slurry oil and furnace oil) co-generation power plant of
510 MW, comprising 325 MW of power generation capacity and 900 tph of steam
capacity.