Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Lupin seeks more time to complete project in Indore SEZ

Friday, 19 Apr 2019
Share this on :
Lupin, a multinational pharmaceutical company, has sought more time from the Commerce Ministry to complete its project in the Indore Special Economic Zone (SEZ).

The company is setting up a pharma unit in the SEZ at a proposed investment of Rs 205.69 crore.

The unit will manufacture pharmaceutical formulations -- metered dose inhalers and dry powder inhalers.

The request for extension of time will be considered by the Board of Approval (BoA) of SEZs in its meeting to be held on 22 April 2019.

The company has sought extension of letter of permission (LoP) beyond 11 April 2019 for one year up to 11 April 2020.

The company received the LoP on 12 April 2016. It has already received two extensions, valid till 11 April 2019.

The Development Commissioner (DC) of Indore SEZ has recommended the company's request to BoA as the unit has made expenditure of Rs 43.11 crore till 28 March 2019. Moreover, construction activities are in full swing and  expected to be completed by November 2019.

The unit has committed to commence production before March 2020.