BGR Energy Systems has won three orders worth Rs 45 crore.
The company has secured an order from CINDA, a subsidiary of Taiwan-based
largest integrated engineering and construction firm CTCI Corporation, for
design, engineering and supply of 72 bundles of air heaters for receiving and
re-gassification terminal of Petronet LNG in Kochi, Kerala. The packages will be
delivered by November 2010.
HPCL - Mittal Energy has awarded a contract for supply of air cooled heat
exchangers for
Guru Gobind Singh Refinery Project at Bhatinda, Punjab. The contract is to
be completed within 8 months. The scope of work includes design, supply,
erection and commissioning of 46 number of air cooled heat exchangers at project
site for naphtha hydro treating unit and vacuum gas oil hydro heating unit.
The company won another order from Essar Oil for supply 30 numbers of air
cooled heat exchangers for its refinery expansion project at
Vadinar, Gujarat.