Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

PMC’s 24x7 water supply project sees slow progress, completion likely by December

Friday, 11 Jul 2025
Share this on :

Eight years after its launch, Pune Municipal Corporation’s (PMC) 24x7 water supply project continues to face delays, with only 25 of the planned 82 overhead water tanks commissioned so far.

While the civic body claims that construction of 66 tanks is complete, 41 remain non-functional due to incomplete supply line connections. Civic officials cited land acquisition as a major challenge causing delays. “The civic administration is generating funds for the project. The funds will be used for building connecting lines between water tanks and taps of end users,” said Nandkishor Jagtap, Head of PMC's water supply department.

The project includes an investment of around Rs 280 crore for tank construction, with capacities ranging from 20 to 40 lakh litres. Currently, 700 km of a planned 1,060 km distribution line is complete, with 70 percent of 3.14 lakh meter installations finished. Rs 1,471 crore of the Rs 2,048 crore project budget has been spent.

Completion is expected by December 2025, with full operationalisation by March 2026.