Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

EC granted for expansion of Indian Oil Corpn’s Gujarat refinery

Wednesday, 15 Jul 2020
Share this on :
The Ministry of Environment, Forest and Climate Change has accorded  environmental clearance (EC) for the Indian Oil Corporation’s expansion/ modernisation of refinery located at Vadodara district of Gujarat.

The capacity will be expanded from 13.7 million tpa to 18 million tpa over an additional area spread across 3,24,000 sq mtr. The refinery spreads across 37,43,000 sq mtr. The recurring cost which includes operation and maintenance will be around Rs 268 lakh per annum.

Some of the products which will be expanded include LPG with a capacity of 529 tpa, polypropylene with a capacity of 402 tpa, and sulphur with a capacity of 49.3 million tpa

The estimated cost of the project is Rs 22,210 crore with a total employment generation of 125 direct jobs and 500 indirect jobs after expansion.

The power requirement of the project is 2,52,800 kVA to be met from the existing captive power plants and grid power infrastructure.

The project was accorded terms of reference (ToR) on 14 April 2018 followed by amendment in ToR dated 1 April 2019 and 4 December 2019.