Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

First crude consignment for Essar refinery arrives

Saturday, 23 Sep 2006
Share this on :

Essar Oil, on 22 September 2006, received its first crude oil consignment of 1 million barrels (around 137 kt)  at the Vadinar port in Gujarat. The second consignment is expected by the end of September 2006.

Essar Oil's 10.5 million tpa refinery will be commissioned in phases. Primary units like the crude distillation unit, sulphur gas unit and the naphtha hydrotreater will be commissioned in the first phase, followed by secondary units like the fluid catalytic cracker and the diesel hydrotreater.

The refinery is fully integrated with its own dedicated 120 MW power plant, port and terminal facilities. It includes an SBM capable of handling vessels up to 3,50,000 dwt with a capacity of 25 million tonnes per year, tankages a marine product dispatch capacity, and rail-car and truck loading facilities.

Also See:

First crude consignment for Essar refinery soon (8-Sep-06)

Related Links:
Project profile

New Password
Confirm Password