Upper Ganges Sugar & Inds, part of the KK
Birla Group, has decided to set up a greenfield sugar plant of 7,000 tccpd in
Uttar Pradesh. The project costing around Rs.275 crore is likely to be
commissioned by 2006-07. It would be the group's first sulphur-free sugar
producing unit and would be equipped with a co-generation power unit. The
location of the project would be ready within the next one month.
The KK Birla Group is planning to invest
Rs.400-450 crore during the next two years in its three sugar companies -- Upper
Ganges Sugar & Industries, Oudh Sugar Mills and Govind Sugar Mills -- and in
the greenfield plant mentioned above.
By 2006-07, the group aims to increase its total
sugar producing capacity to 50,000 tonnes crushed per day (tccpd) from the
existing level of 40,000 tccpd.
A Rs.90 crore capacity expansion programme is
currently on at Oudh Sugar where the capacity is being increased to 10,000 tcd
from 7,500 tcd. The distillery capacity is also being increased to 125
kilolitres per day (klpd) from 65 klpd.
A capacity expansion programme costing Rs.50-100 crore is
likely to be taken up at Govind Sugar Mills during 2006-07.
In another development, the
Bihar government has disapproved the group's plan of relocating its Samasthipur
unit in the state to Uttar Pradesh. The Samasthipur unit was perennially beset
by floods causing significant losses. The KK Birla Group had proposed to
relocate the unit to Uttar Pradesh with an eventual objective of merging it with
Upper Ganges Sugar. The Bihar government has assured the Group that it would
create necessary infrastructure to insulate the unit from flood damage.
Sugar
Companies of KK Birla Group
|
(Key: OSML:Oudh
Sugar Mills, UGSIL:Upper Ganges Sugar & Inds, GSL:Govind
Sugars, NISM=New India Sugar Mills) |
Location |
District |
State |
Company |
Capacity* |
Narkatiaganj |
West Champaran |
Bihar |
OSML |
5,000 |
Hargaon |
Sitapur |
Uttar Pradesh |
OSML |
5,000 |
Rosa |
Shahjahanpur |
Uttar Pradesh |
OSML |
3,500 |
Seohara |
Bijnor |
Uttar Pradesh |
UGSIL |
11,000 |
Sidhwala |
Gopalganj |
Bihar |
UGSIL |
2,500 |
Aira Estate |
Lakhimpur Kheri |
Uttar Pradesh |
GSL |
3,500 |
Hansanpur |
Samastipur |
Bihar |
NISM |
1,750 |
Total
capacity for seven units spread over two states |
35,250 |