Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NSL Renewable mops up funds for hydel projects in Himachal

Thursday, 15 Apr 2010
Share this on :

NSL Renewable Power, the 100 per cent subsidiary of Hyderabad based NSL Group, has achieved financial closure for its three hydel power projects - with a combined capacity of 155 MW - being set up in Himachal Pradesh.

The projects entail a cost of Rs 996 crore with a debt-equity ratio of 70:30. The equity portion of about Rs 280 crore is likely to come from internal accruals including from the NSL Group.

The company is setting up a 100 MW plant at Tidang in Kinnaur district at an estimated cost of Rs 650 crore, two units of 44 MW and 6 MW are coming up at Tangnu Romai with an outlay of Rs 319 crore and a 5 MW plant at Masli for Rs 27 crore.

The Tidang and the 44 MW Tangnu projects are likely to be completed in March 2013 while the 6 MW project will be commissioned by March 2012. The Masli plant is slated for completion by December 2010.