Expressways, SEZs may come up
alongside
The Union Ministry of Road Transport & Highways
is likely to allow real estate developers to tie up with
road developers for setting up SEZs alongside
expressways.
According to sources, the construction cost of
expressways is almost Rs 20 crore per km and
therefore can pose difficulties for road developers to
fund such huge projects on their own.
Thus, expressways can be commercialised by setting
up SEZs. The road developers can tie up with real
estate players and bid for the project.
NHAI likely to have more powers
The NHAI is likely to be able to exercise more
powers on decisions related to bidding for roadway
projects after the Cabinet Committee on
Infrastructure (CCI) accepted a slew of
recommendations made by the committee.
As a result, NHAI can now accept a single bid after
reasonable consideration, which earlier used to go to
the Cabinet for approval. Till now, any road project
was to be awarded only if it got at least two bids.
Also, to bring down procedural delays, the RFQ, once
submitted and qualified, will remain valid for one year from the date of submitting the RFQ or valid till 30
September, whichever comes early. Earlier, a bidder
had to go through the process all the time.
The committee had also recommended providing
powers to NHAI to change the RFP and RFQ norms,
which were approved by the Union Ministry of
Road Transport and Highways. Earlier, such changes
were done by the Planning Commission.
NHAI nod for few restructured projects
The NHAI has reportedly approved that all projects
where the value change after restructuring was
below 20 per cent of the total project cost (TPC) will
be cleared by the board. The ones with over 20 per
cent variation will be referred to the Union
Government for approval.
This is expected to fast-track clearance of the
restructured highway projects. Nearly 35 projects
tendered during 2008 were restructured till June
2009, as these received no bidders. The TPC of
most of these projects was increased after
reassessment of engineering was done.
The NHAI board has agreed that projects cleared by
the board shall not need PPP Appraisal Committee
clearance. However, it will refer the case to the
ministry for its nod.
|