Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Adani Power commences power supply to Bangladesh from Godda plant in Jharkhand

Monday, 10 Apr 2023
Share this on :

Adani Power (APL) has commissioned the first 800 MW ultra-super-critical thermal power generation unit at Godda in Jharkhand, and also commenced the supply of 748 MW to Bangladesh.

The Godda plant is the first power plant in India, which has started its operations with 100 percent flue gas desulphurization (FGD), selective catalytic reduction (SCR) and zero water discharge.  It comprises two units of the latest technology, which is ultra super critical technology with the latest techniques for controlling emissions and consumption of coal and water. These features make it the most efficient and environment-friendly thermal power plant installed in India and the entire South-East region.

Adani Power Jharkhand (APJL) had set up the first unit with the power grid of Bangladesh in November, 2022 through a dedicated transmission line from Godda to Bangladesh. The requisite transmission evacuation system on the Bangladesh side was commissioned in March 2023. Accordingly, APJL again synchronised unit 1 on 20 March 2023.

The reliability run test, including commercial operation tests, was completed on 5 April, 2023 under the supervision of Bangladesh Power Development Board (BPDB) and Power Grid Corporation  (PGCIL). The plant is also a strategic asset for both India and Bangladesh, to the extent that it will ease power supply in Bangladesh.

In November 2017, Bangladesh Power Development Board (BPDB) had executed a long-term power purchase agreement (PPA) with APJL to procure 1,496 MW net capacity power from the 2X800 MW ultra-supercritical power project at Godda.