Union Minister Jyotiraditya Scindia reviewed the progress of key development projects in Gwalior during a meeting at the Gwalior collectorate on 15 September, 2025, emphasising timely completion and quality work.
Deadlines were set for major projects including the Gwalior Elevated Road: Phase-1 (Rs 446.92 crore) is slated for completion by 01 October, 2027, and Phase-2 (Rs 926.21 crore) by 19November, 2027, aimed at easing city traffic. The Rs 534.70 crore renovation of Gwalior railway station, featuring new platforms and modern passenger amenities while preserving heritage, will be completed by April 2026.
Additionally, land acquisition for the Rs 4,613 crore Agra-Gwalior Expressway has begun, expected to boost industrial and commercial growth in the region. Officials were urged to avoid delays causing inconvenience to the public.
Minister Scindia stressed the importance of accelerating infrastructure, education, health, sanitation, and public facility projects to transform Gwalior into an ideal district, leveraging its rich historical and cultural heritage.