Dilip Buildcon has received provisional completion certificate for Anandpuram-Pendurthi-Anakapalli section in Andhra Pradesh.
The project involved six-laning of Anandapuram-Pendurthi-Atrakapali Section of NH-5 (new NH-16) from 681.000 km (existing 681.000 km) to 731.780 km (existing 742.400 km) (design length - 50.780 km) in Andhra Pradesh under Bharatmala Pariyojana on hybrid annuity mode (HAM) has been provisionally completed.
The provisional completion certificate has been issued by the authority and had declared the project fit for entry into commercial operation as on 8 November 2021.
The cost of the project is Rs 2,013 crore. The appointed date for the road project was 4 January 2019 with scheduled completion date of 1 July 2021. The revised scheduled completion date including EOT on account of COVID -19 is 8 November 2021.