Intek Asia-Pacific of Malaysia, consultants to
Kochi Refineries' Rs.780 crore crude oil receipt facilities project, would
submit their revised cost estimate report in June 2005. The report would be
taken up for approval in the KRL board meeting in July 2005.
The project would now be executed on
"conventional method" basis that means that contractors will be
appointed for taking up distinct project segments. KRL had earlier planned to
implement the project on a turnkey basis. The cost escalation, coming from
rising steel prices, is to the extent of 40 per cent above the approved cost of
Rs.780 crore. If the company goes in for the turnkey approach, the project cost
would work out to Rs.900 crore. The facility at Puthuvypeen Island near here is
scheduled to become operational by May 2007.
Project details: The project involves laying of
a 48-inch submarine pipeline for a distance of 20 km from the single buoy
mooring (SBM) location to the shore tank farm and from there 30-inch pipeline
covering 6 km to connect the existing pipeline would also have to be laid.
The crude oil receipt facilities consisting of
SBM, a shore tank farm and connected pipelines was mooted to reduce the cost of
crude oil transport and handling as part of the Rs 3,000-crore expansion
programme of KRL to be completed by 2010, wherein petroleum refining capacity
would be raised from 7.5 million tpa to 13.5 million tpa. Engineers India Ltd
prepared the detailed feasibility report that was approved by the KRL board.