Maharashtra State Power Generation Company (MAHAGENCO) has invited tenders
from interested entities for setting up a combined cycle power plant (CCPP) at
existing gas turbine power station at Uran in Raigad district of Maharashtra.
The scope of work includes design, engineering, manufacture, assembly,
testing at manufacturing works, supply, erection, testing, commissioning and
performance guarantee test of CCPP; comprising advance class gas turbine
generators, heat recovery steam generators, steam turbine generators and other
auxiliary equipments including civil works on lum-sum turnkey basis, having
maximum gross plant output of 1,220 MW at site conditions.
The final date of submission of bids is 29 May 2010.
Related Links:
Tender
Project profile