Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NRL refinery expansion project to be completed by 2025

Monday, 12 Aug 2024
Share this on :

The expansion project of the Numaligarh Refinery (NRL) in Assam is expected to be completed by December 2025. The expansion will facilitate capacity to increase to nine million tpa from the present three million tonne. The cost of the NRL expansion project project is around Rs 28,000 crore.

Currently, the physical progress is 65 percent. Total equity contribution will be around Rs 5,500 crore for this project with 69 percent as Oil India’s share. Rs 19,000 crore has already been invested in the project. Post its expansion, the refinery will operate at 50-60 percent capacity before running at its full capacity from 2026-27 once it stabilises.

NRL's expansion includes installing a six million tpa capacity refinery and associated crude oil terminals and pipeline, considering processing of Arab Light and Arab Heavy grades of crude oil. Also, the Assam government has increased its stake in the refinery from 12.35 percent to 26 percent. 

Additionally, a cross country pipeline of around 1,640 km will be laid from Paradip Port in Odisha to Numaligarh for transporting nine MMTPA of imported crude. 

Besides this, Oil India now plans to drill 78 wells in 2024-25 against 61 wells drilled in FY24, and targets to drill 100 wells in the subsequent years. The firm expects gas output to increase after the completion of the gas pipeline connecting Oil India’s producing fields to the national gas grid. The first phase of the pipeline being laid out by Indradhanush Gas Grid (IGGL), a joint venture of IOCL, ONGC, GAIL, OIL and NRL is expected to be completed by December this year. 