Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NTPC awards two contracts for Vindhyachal STPP

Tuesday, 02 Jul 2013
Share this on :

NTPC has awarded two contracts for Vindhyachal super thermal power project (STPP), Stage-V (1 x 500 MW) at Vindhyanagar, Singrauli in Sidhi district of Madhya Pradesh.


McNally Bharat Engineering has received an order worth Rs 108.94 crore for setting up a coal handling plant at the project site. Completion period scheduled for the plant is 26 months.


Petron Engineering Construction has bagged a contract worth Rs 32.29 crore for supply of electrical equipment, inland transportation, insurance, installation, testing, and commissioning and conducting guarantee tests of electrical equipment for the project.


Vindhyachal STPP involves setting up of a coal-based power unit with an installed capacity of 500 MW. Total coal requirement for the project will be 2.5 million tpa. Domestic coal will be sourced from Pakri Barwadih coal Block in Jharkhand.

 