National Highways Authority of India
has made average progress as far as actual completion of projects under the
National Highways Development Programme is concerned, according to a special
study done by ProjectsToday based on official statistics released NHAI.
During the twelve-month period ending
30 June 2006, NHAI added a total of 650 km of national highways across its
project segments -- Golden Quadrilateral, North-South East-West Corridor and
Phase-III A. This translates to an average addition of only 1.8 km per calendar
day during the period.
Out of the 650 km of highways
constructed, 497 km (or 76 per cent) belonged to the Golden Quadrilateral
project that aims at connecting the four metros -- Mumbai, Delhi, Kolkata and
Chennai -- through a highway network spanning 5,846 km. As of 30 June 2006, the
GQ segment stood 92.5 per cent complete, as against the corresponding 84 per
cent as of 30 June 2005. The Union government has targeted achieve a completion
rate of 95.6 per cent (or 5,360 km) by 31 December 2006. The government
apprehends that 238 km of stretches will remain unfinished at least up to 31
December 2006. Incidentally, over 50 per cent (or 120 km) of these stretches,
envisaged to remain incomplete, lie on the 1,453-km Delhi-Kolkata arm of the GQ.
The original target completion date for GQ was December 2003.
The rate of completion on the
North-South East-West corridor (Phase II of the NHDP) has been quite poor during
the 12-month period ending June 2006. NHAI added only 123 km of highways under
this project segment, accounting for 19 per cent of the total addition in the
period. However, NHAI appears to have done well in terms of awarding contracts.
As of 30 June 2006, the total number of contracts awarded under NHDP-II stood at
137 for a total length of 5,063 km. As of June 2005, the total number of
contracts awarded under NHDP-II stood at a much smaller 26 for a total length of
2,459 km. The target completion timeframe for NHDP-II is end-2010.
It may be noted here that awarding of
contract does not necessarily mean commencement of work. NHAI's official
statistics do not reveal statistics on the current status of contract awarded.
NHAI treats award of contract as a project under implementation. It is common
knowledge that land acquisition is the biggest hurdle for national highway
projects and that contracts are technically "under implementation"
with little or no groundwork. In a press report of February 2006, it was
estimated that the NHAI had acquired only 15 per cent (or 2,369 ha) of land out
of the total requirement of 15,892 ha for NHDP-Phase II. Land acquisition,
according to this reportage, was very poor in all the four southern states of
India.
Returning to NHAI's performance during
the year ending June 2006, a notable feature was the completion of the first
segment of Phase III in August 2005. Phase III involves the four-laning of
10,000 km of national highways not covered in the earlier two phases. Phase
III-A, involving some 4,000 km, would be taken up first. As of 30 June 2006,
NHAI had completed an insignificant portion (30 km) of Phase III-A but 17
contracts were under implementation together covering 1,090 km.
The overall completion rate of NHDP
(Phases I, II and III-A) was 36.5 per cent as of 30 June 2006. As of same date,
38.4 per cent was under implementation while 24.4 per cent was pending.
Very recently, NHAI made another
achievement by awarding the first contract under NHDP-Phase V. Under this phase,
NHAI would be six-laning around 6,500 km of national highways including portions
of the already four-laned Golden Quadrilateral. The total cost of NHDP-V is an
estimated Rs.41,210 crore. The first contract was awarded to a IDAA
Infrastructure Pvt Ltd (a consortium of four companies including Mumbai-based
Ideal Road Builders) for the 65-km Bharuch-Surat section on NH-8 in Gujarat, on
BOT basis. This project, very importantly, involved a negative grant of Rs.504
crore that was the highest ever received by NHAI.
prjexcl