Alstom Projects India secured two contracts worth Rs 1,267.70 crore from GVK
Industries to build two units at the new Jegurupadu-III combined cycle power
plant in East Godavari district of Andhra Pradesh.
The company will design, manufacture, supply, install, test and commission
the two units, each consisting of Alstom's GT26 gas turbine, steam turbine,
generator, heat recovery steam generator (HRSG), associated civil works and
balance of plant equipment. The gas turbine, steam turbine, generator and HRSG
are to be manufactured at Alstom's facilities in Europe and Asia.
The project is slated to be commissioned from 2013 onwards and will be based
on single-shaft configuration and will have a combined power output of 800 MW.
Related Links:
Project profile