Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

NTPC inks PPA for Kudigi plant

Monday, 08 Nov 2010
Share this on :

NTPC on 4 November 2010 signed a PPA for its power plant in Karnataka.

The company signed the PPA with the electricity supply companies of the state (Escoms) of Karnataka for the 4,000 MW super-critical thermal power plant at Kudigi.

The proposed plant is to come up at an estimated cost of Rs 24,000 crore. The plant to be developed in phased manner is likely to have five units of 800 MW each when fully commissioned

The total area required for the project is about 3,500 acre which includes 1,900 acre for the main plant and 1,100 acre for the ash pond area and 250 acre of township. The water requirement will be 5.2 thousand million cubic ft per annum from the Almatti dam.

Currently, the company is waiting for the land acquisition process to be completed by the state government.