Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Unit-I of Lanco's Kondapalli project to ready by end-October

Wednesday, 21 Oct 2009
Share this on :

Lanco Infratech is likely to commission the first unit of Kondapalli expansion project in Andhra Pradesh by end-October 2009.

The company has secured natural gas linkage assurance from Reliance Industries' Krishna-Godavari basin gas fields for the 368 MW Lanco Kondapalli combined cycle power plant expansion project. While the first unit of 240 MW is likely to commence operations by end-October 2009, the second unit will be ready by December 2009.

The company is also executing the 600x2 MW imported coal based project in Karnataka through Udupi Power Corporation. The first unit of 600 MW is expected to be synchronised with the grid by March 2010 and the second unit within six months thereafter.

Also See:

Bids invited for Lanco's Kondapalli gas based power plant (23-Sep-09)