L&T has bagged two orders worth a total Rs 581 crore from Powergen
Infrastructure and Bangalore Water Supply and Sewerage Board (BWSSB). These
projects are to be executed by the metallurgical, material handling and water
operating company of L&T's construction division.
Powergen Infrastructure has awarded an order valued at Rs 392 crore for
setting up a coal handling plant at 5x660 MW
Tiroda thermal power plant of Adani Power in Maharashtra. The scope of work
includes basic and detailed engineering, supply and erection of mechanical,
electrical & instrumentation systems, and structural steel works including
testing and commissioning. This greenfield project is to be set up in 30 months.
The Rs 189-crore order secured from BWSSB involves fabrication and laying
mild steel pipeline from
Harohalli to Tataguni and Vajarahalli, along with associated civil work. The
scheme envisaged transmission of 5,000 million litres per day clear water from
Cauvery river (Shiva Balancing Reservoir) to Bangalore.