Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Orissa Govt seeks changes in RfQ norms for UMPP

Tuesday, 24 Sep 2013
Share this on :

The Orissa Government has sought sanction from the Ministry of Power & Natural Gas to make changes in the RfQ document for the proposed ultra mega power plant (UMPP), at Bedabahal in Sundargarh district.

 

As per the new standard bidding documents (SBDs) prepared by the ministry, the state utility has to obtain all approvals, permission, licence and statutory clearances for the projects and coal block development within 120 days of signing the power purchase agreement (PPA). It will be a tough task for the state utility to complete the assignment within such a short time.

 

Hence, the state government has requested the ministry to modify the provisions in the model PPA for transferring the project to the successful bidder on as-is-where-is basis.

 

Gridco, the state utility, being the major power buyer from the proposed UMPP with 4,000 MW capacity, is the lead member for the Bedabahal project. It will purchase 32 per cent of power to be generated from the UMPP.

 

The ministry has cancelled the tender for the proposed project floated in 2010. The proposal for invitation remained suspended due to lack of environment clearance for captive coal blocks allotted to the project. But once again the bidding process was delayed due to framing of new SBDs, which were finalised last month.

 