Patel Engineering bagged an order worth
Rs.695.57 crore from Andhra Pradesh government for the modernisation of Krishna
Delta System. The project is a part of the numerous modernisation programmes
undertaken by the state government on major river delta systems to boost
irrigation potential.
The project work will involve
development of Bantumilli Canal (from KM 58.105 to 100.383), Polarj Canal (KM
58.105 to 100.36), Campbell Canal (KM 58.105 to 96.289), Dosapadu Channel (from
KM 0.000 to 35.085), Kunderu Channel, East Bank Canal (from KM 7.738 to 64.50)
(Package 4), Gudivada Channel ((KM 0.000 to 39.937) and its distributaries and
for Prakasam Barrage on EPC turnkey basis.
The projects are expected to be
completed within 36 months.