Road construction company, Dilip Buildcon (DBL) has received the provisional completion certificate as declaration of commercial operation date (COD) for road work on NH-78 in Madhya Pradesh.
The project envisages rehabilitation and upgradation of the existing road to two lane with paved shoulder as cement concrete pavement configuration Katni-Shahdol-Anuppur to MP/Chhattisgarh border (NH-78), from the existing 142/200 km to 245/0 km (design length 91.800 km) on engineering, procurement and construction (EPC) basis.
The company completed the project 100 days prior to the scheduled completion date. The road project has been declared fit for entry into commercial operations from 17 February, 2017.