Municipal Administration and Urban Development (MAUD) Minister for Telangana KT Rama Rao inaugurated the right hand side (RHS) flyover at Kamineni Junction on 28 May 2020.
The work on the project worth Rs 43 crore commenced on 18 August 2018 with completion and was completed on 25 May 2020. The entire project entails an investment of Rs 448 crore.
The scope of work involved construction of multilevel/ grade separators at four junctions at LB Nagar and surroundings in Hyderabad under Package-II of Strategic Road Development Programme (SRDP) Phase-I.
The total length of the flyover is 940 mtr.
The project will help in free flow of inner ring road traffic from Secunderabad to Owisi & Srisailam through this flyover.
Kamineni LHS Flyover was already completed and in operation.