Sunil Hitech Engineers has bagged
two orders amounting to Rs.152.4 crore from Maharashtra State Power
Generation Co. as follows
Complete supply, fabrications &
erection of structural steel required in main plant building, bunker buy &
miscellaneous structure for 1x250 MW new Parli project (Unit 2) [contract value:
Rs.76.3 crore]. (project
details)
Complete supply, fabrication &
erection of structural steel required in main plant building, bunker bay &
miscellaneous structure for 1x250 MW Paras thermal power expansion project (Unit
2) [contract value: Rs.76 crore] (project
details)
Work on both these orders is scheduled
for completion within 24 months.