Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Talcher power project commissioned

Tuesday, 08 Feb 2005
Share this on :

National Thermal Power Corporation has commissioned a 500 MW unit at its Talcher thermal power project at Kaniha in Angul district of Orissa. With this, the total capacity of the plant stands at 3,000 MW.

NTPC had embarked on this Rs.8,700 crore expansion project that involved the setting up of four units of 500 MW each, in January 2000. The plant already had two units of 500 MW in operation, before the expansion plan was launched.

The first three units of the expansion project were commissioned in February 2003, November 2003 and May 2004, respectively.

The entire project has been completed one year ahead of its original scheduled completion date of 28 February 2006.