The Telangana Super Thermal Power Project of two x 800 MW coming up at Ramagundam is gearing up for trial runs of boiler and turbine auxiliary systems with the existing 400 kV switchyard of NTPC being connected.
A total of three 400 kV bays have been erected and commissioned in the existing NTPC-Ramagundam switchyard area besides laying 400 kV double circuit line from there to the Telangana Project GIS switchyard.
The equipment and power connectivity for the project was commissioned on 24 June 2020.
The 400 kV GIS switchyard of the Telangana Super Thermal Power Project is among four such switchyards of NTPC.