The Telangana State Power Generation Corporation (TSGENCO) has commissioned Unit-1 of 270 MW of 270 x four MW of Bhadradri Thermal Power Station.
The Unit-1 has been synchronised with the grid with an initial load of 20 MW. It reached a maximum load of 35 MW. Later, on confirming normalcy at all points, the unit was hand-tripped for taking up further activities. All other units of 270 MW each are in full swing and expected to be commissioned and synchronised by the end of 2019.
Commissioning of the project is being delayed due to extreme weather conditions and non-availability of professional labour at the site.