Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Unit I of Kakrapar project to commission in 2015

Wednesday, 21 Apr 2010
Share this on :

NPCIL's 700 MW pressurised heavy water reactor at Kakrapar Atomic Power Project (KAPP) in Surat district of Gujarat is expected to be commissioned in 2015.

Around 70 per cent of excavation of the site of KAPP Unit I has been completed and the first 'pour of concrete' (for laying the foundation) is likely to take place in June 2010.

Work on Unit II of 700 MW in KAPP will begin after six months. The cost of two plants is Rs 11,500 crore. In December 2009, NPCIL awarded the reactor building contract, of both units to L&T valued at Rs 844 crore.

Also See:

L&T bags order for Kakrapar power project (08-Dec-09) 