The Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) is setting up a tertiary treatment reverse osmosis (TTRO) plant at Koyambedu in Chennai district, Tamil Nadu.
The annual production capacity of the plant is 45 MLD. As confirmed with Projects Today, around 15 percent work is complete.
The cost of the project is Rs 594 crore. Engineers India has been appointed as consultant for preparing the detailed project report (DPR) and VA Tech Wabag in partnership with IDE Technologies were appointed as construction and operation and maintenance (O&M) contractor.