The railway ministry, in a bid to start work at
the earliest on the proposed freight corridor, being sponsored by the Japanese
government, has sought early finalisation of the feasibility report.
The corridor will connect the four metros
exclusively for freight traffic and will run along the Golden Quadilateral.
Though the feasibility report, work on which
began in early 2005 by Japanese company Jica, is expected to take two years, the
ministry wants at least part of the Rs 22,000 crore loan amount for the first
phase to come through so that work can begin.
The total project is expected to cost Rs 60,000
crore for which the feasibility report from the Indian side is being conducted
by Rites. This report is expected to come out by December.
The Japanese government had told the Indian
government that it would be completing the study in three years, as that is a
normal timespan for a project of such magnitude.
But after the request from the Railway ministry,
it was mutually decided that the report would be completed in two years.
However, Railway Board chairman JP Batra have
again requested Jica to complete its report within 18 months, as they want to
start the project by early 2006.
Significantly, the Railway ministry has proposed
that work on the project can start simultaneously while the feasibility reports
are being prepared.
Japanese assistance of Rs 22,000 crore would meet
30% of the total project cost.
This would be a tied loan (wherein there is no
possibility of global bidding) and Japan would be the main facilitator of the
project, while the sub-contractors could be from any other country.
The loan would carry 4% interest with a 40-year
repayment period and 10 years' grace period. It would be mainly for the
Delhi-Mumbai corridor, which is the first phase of the project.