Mumbai-based Valecha Engineering, on
22 March 2006, bagged an order valued at Rs.63 crore from Jammu & Kashmir Public
Works Department, for construction of four bridges.
As per the contract, Valecha will
build four major bridges and one flyover on Srinagar Bypass of NHAI. The
proposed bridges will have PSC Box/RCC Box type construction with well
foundations.
The length of the four bridges would
be 186.8m, 79.3m, 130.8m and 309.1m respectively. The flyover will be 340.5m
long.
The contract would be completed within
24 months.