Reach us: 7304553123 / mktg@projectstoday.com
Help
1. Boolean Searches :

i. AND - Shows results where both terms on either side of the 'AND' operator are present. 'AND' must be in upper case. For example search term - delhi AND metro result - It will return records in which 'delhi' as well as 'metro' both are present.

ii. OR - Shows results where either term (or both terms) is present. 'OR' must be in upper case. For example search term - delhi OR metro result - It will return records in which either 'delhi' or 'metro' or both are present

2. Proximity Searches

A proximity search looks for terms that are within a specific distance from one another. For example, search term - 'delhi metro'~10 result - It will search for records where 'delhi' and 'metro' are found within 10 words of each other

3. Phrase searches

You can search phrases using double quotes. for e.g. 'delhi metro' result - It will return records where 'delhi metro' phrase is found.

Contract awarded for integrated steel plant at Raichur

Monday, 14 May 2007
Share this on :

Surana Industries has awarded the contract worth Rs.58 crore for boilers, ESP & turbine for 35 MW captive power plant for the integrated steel plant in Raichur district Karnataka.

The company has placed order of Rs.36 crore to Cethar Vessels, Trichy for boilers, Rs.14 crores to Qingdao Jieneng Power Station Engineering Co, China and Associated Power Team, Hyderabad for Turbine and Rs.8 crore to Thermax, Pune for ESP.

Through this contract Cethar Vessels will install design engineering, manufacture, assembly, erection, startup, testing, commissioning and guarantee performance Testing of (1) No. of 110 tph, 66 ksca,495 + 5 deg C Fluidised Bed Combustion Boiler and its auxiliaries and four (4) Nos of 10.5 TPH,68 ksca,495 + 5 C waste heat recovery boiler and auxiliaries.

Qingdao Jieneng Power station Engineering, china and Associated Power Team, Hyderabad, will install design, engineering, manufacture, assembly, testing, erection, Ssart up, commissioning & guarantee performance testing of 35 MW Tturbo generator and auxiliaries.

Thermax, Pune will install design, engineering, manufacture, assembly, erection, startup, testing, commissioning and guarantee performance Ttsting of (4) Nos of ESP, ID Fan and Flue gas ducting work for 10.5 tph WHRB and 1 Nos of ESP for 1x110 tph AFBC boiler.

The proposed steel plant, being developed at a total investment of Rs.473 crore will have capacity to produce 1.28 lakh tpa of sponge iron, 2.25 lakh tpa of steel melting shop and 2 lakhs tpa of rolling mill annually. The plant will have 30 MW captive power plant. The plant is expected to be operational by March 2008.

Related Links:
Project profile

New Password