Larsen & Toubro bagged an order worth
Rs.287 crore from Mumbai Metropolitan Region Development Authority (MMRDA) for
the construction of elevated access road from Western Express Highway (WEH),
Mumbai, to the Chatrapathi Shivaji International Airport (CSIA).
The scope of work involves design and
construction of 1,850 m long six-lane corridor consisting of pedestrian and
vehicular subways, resurfacing of roads at western express highway including the
construction of a 1,150 m long, six-lane elevated access road as well as one 165
m long tunnel. The elevated access road will be built using segmental
construction technique.
The work order is expected to be
completed within 30 months.