Sadbhav Engineering bagged an order
worth Rs.310.20 crore for execution of Omkareshwar project canal system
(Phase-III) comprising of right bank flow canal from RD 68.92 km to 162.95km
including distribution net work upto 40 ha chak for irrigating C.C.A of about
48592 ha on turn-key basis.
The scope of work includes work of
survey, planning, design, estimation, preparation of land acquisition cases,
construction of canal by excavation/and earth work, cement concrete lining, all
inline concrete structures like VRB/DRB/NHB/SHB, C.D. works, aqueducts, super
passages, falls, head/cross-regulators, escapes, outlets etc and commissioning
of canal system.